When this is not a formal part of the closeout process, it often gets missed. It is easy to add a Project Level User Defined field for “Archive Date” in P6 and fill in this date as part of the project closeout process while the contractual requirements are fresh in everyone’s mind.
#Backup primavera p6 oracle database how to#
How to track the date to archive the P6 project? Monthly backup schedules are priceless when you are in a claims situation, so think long and hard about whether these should be kept. Typically, there are many what-if and backup copies of the project as well, and the project team should look at which of these are required.

(Alternatively, the key project information could stored be in a datawarehouse like EP-datawarehouse rather than keeping the entire project.)Īll of these factors can be difficult to track after the fact, so we normally recommend that clients decide how long a project should be kept as part of their formal project closeout process.